ADEOS Operation History (2)


Year Month Date Events
1996 Aug. 17 Launch
28 RIS Checkout Start
Sep. 1 AVNIR Mu Checkout Start
3 AVNIR Pa Checkout Start
4 OCTS VNIR Checkout Start
10 NSCAT Checkout Start
TOMS Checkout Start
16 POLDER Checkout Start
17(L+1M) ILAS Checkout Start
TOMS Early Routine Operation start
20 IMG Checkout Start
21 TOMS Near Real-Time Data Distribution
Oct. 1 OCTS IR Checkout Start
14 Start of OCTS Observation
17(L+2M) OCTS Near Real-Time Data Distribution
Nov. 1 TOMS Calibration Complete
2(L+2.5M) ILAS Routine Operation Start
RIS Routine Operation Start
17(L+3M) OCTS Tentative Distribution
OCTS Routine Operation Start
AVNIR Tentative Distribution
AVNIR Routine Operation Start
NSCAT Preliminary Calibration Complete
POLDER Routine Operation Start
IMG Tentative Distribution
IMG Routine Operation Start
ILAS Tentative Distribution
RIS Tentative Distribution
Dec. 17(L+4M) NSCAT Tentative Distribution
1997 Jan. 17(L+5M) NSCAT Primary Calibration Complete
Mar. 17(L+7M) NSCAT Near Real-Time Data L-2' Distribution
Apr. 17(L+8M) AVNIR Data Distribution
POLDER Level-1 Calibrated Data Distribution
IMG Data Distribution
May 1(L+8/9M) POLDER Interim (Non-Validated) Products for PIs
17(L+9M) TOMS Data Distribution
Jun. 17(L+10M) OCTS Preliminary Data Distribution
Aug. 17(L+12M) RIS Verified Data Distribution
Oct. 17(L+14M) POLDER Level-2,3 Data Distribution
Dec. 17(L+16M) NSCAT Routine Operation Start
1998 Jan. 17(L+17M) NSCAT Data Distribution
May 17(L+21M) ILAS Verified Data Distribution

(L:Launch Date, M:Month)

--